Double Unit Buildout
Pad for Building C poured.
Nearing Building B vertical completion.
Building B progress, paving prep and Building A nearing completion.
Building B progress, paving prep and Building A nearing completion.
25′ Unit Mezzanine, Bathroom Framing & Temp Stairs/Railing.
Building B Vertical Construction Progress
Drone photo by: Richard W. Roessler
Roof installation complete
Roof arrives for Building A. Internal structure complete.
Drone photo by: Richard W. Roessler
Building A outer walls complete
Drone photo by: Richard W. Roessler
North side of Building A completed
140mph rated interlocking & insulated wall paneling installation.
Building A structure & Building B foundation flyover.
Drone video by: Richard W. Roessler
Foundation pour for Building B complete
Aerial picture by: Richard W. Roessler
Building A vertical construction is complete!
Building A continues vertical progress
Steel arrives and commencement of vertical construction of Building A begins.
85 trucks of concrete arrive to pour pad for Building A
Plumbing complete for Building A
Concrete pilings poured for Building A
Sitework commences on 15 acre Sebring Motor Garages