DEVELOPMENT PROGRESS

July 15th, 2024

Mezzannine stairs and railing installation.  Final power hookup and conditioning of units scheduled for August 2024.

July 5th, 2024

Interior finishings nearly complete.  Painting is being done as we speak, cabinets and stairs on the 15th!  Planned completion end of month for first set of units. (Pictured is double wide unit with 10′ mezzanine)

June 10th, 2024

The long awaiting opening of Sebring Motor Garages & Townhomes is now in sight!

Our greatest two challenges have been delays with Duke Energy and Comcast. It has taken many months for the engineering departments of these two companies to approve designs, thus allowing us to install underground sleeving prior to paving as well as securing the actual power and cable services.

With designs now approved, underground sleeving is in progress. Duke Energy transformer pads are now being set allowing us to commence the installation of the first lift of asphalt for the entire complex in the coming weeks followed by landscaping, fencing, gates and powering up of HVAC units to complete interior buildouts that require climate control.

April 29th, 2024

Double Unit Buildout

April 24th, 2024

Pad for Building C poured.

March 18th, 2024

Nearing Building B vertical completion.

March 13th, 2024

Building B progress, paving prep and Building A nearing completion.

March 1st, 2024

Building B progress, paving prep and Building A nearing completion.

February 16th, 2024

25′ Unit Mezzanine, Bathroom Framing & Temp Stairs/Railing.

February 7th, 2024

Building B Vertical Construction Progress

January 27th, 2024

Roof installation complete

January 15th, 2024

Roof arrives for Building A. Internal structure complete.

January 3rd, 2024

Building A outer walls complete

December 27th, 2023

North side of Building A completed

December 20th, 2023

140mph rated interlocking & insulated wall paneling installation.

December 10th, 2023

Foundation pour for Building B complete

December 8th, 2023

Building A vertical construction is complete!

NOVEMBER 30TH, 2023

Building A continues vertical progress

NOVEMBER 28TH, 2023

Steel arrives and commencement of vertical construction of Building A begins.

November 18th, 2023

85 trucks of concrete arrive to pour pad for Building A

November 5th, 2023

Plumbing complete for Building A

october 18th, 2023

Concrete pilings poured for Building A

September 14th, 2023

Sitework commences on 15 acre Sebring Motor Garages